Skip to content
Back to CSR Partnerships
CSR Case Study

What ₹40 Lakh of CSR Funding Actually Produced

Cochin Shipyard Limited gave Bal Sansar Sanstha ₹40 Lakh to build a community health centre in a village in Ajmer district. This is the record of how that money was spent and what it produced — including the parts that went wrong.

₹40,00,000
CSR grant, in full
1,517 sq. ft.
Built and handed over
18 months
Concept note to inauguration
100%
Grant utilised and certified
Ribbon cutting at the Aarogyam Kendra inauguration, 26 January 2026
The Kendra declared open, 26 January 2026, with Sh. Sambath Kumar P. N., Advisor (CSR), Cochin Shipyard Limited
The Outcomeपरिणाम

A building that exists

The Aarogyam Kendra is a 1,517 sq. ft. facility on land owned by Bal Sansar Sanstha at our Hathikhera campus: a hall for yoga, naturopathy sessions, health camps and awareness activities, a counselling room, a doctor's consultation room, a staff room, a store and washrooms — with electrical, water and sanitary fittings completed.

It was inaugurated on the 77th Republic Day, 26 January 2026, in the presence of the donor's representatives, BSS Board members, community members, and the students and parents of Bal Sansar Public School. Cochin Shipyard's support is permanently recorded on a stone board at the entrance.

The centre is designed to serve at least 1,000 families a year from Hathikhera and the surrounding villages.

The Recordकार्य-क्रम

Eighteen months, step by step

Every date below is documented in the project completion report submitted to Cochin Shipyard Limited.

July 2024

Concept note submitted to Cochin Shipyard Limited.

October 2024

CSL due diligence — the Head (CSR) and Manager (CSR) visited the Ajmer campus in person.

29 November 2024

Partnership agreement signed.

January 2025

First grant tranche of ₹20 Lakh received.

February 2025

Bhumi Pujan and foundation marking; construction begins.

March – May 2025

Foundation, steel work, column fixing at 7.5 ft, footing and DPC / plinth level.

July 2025

Structure completed.

16 August 2025

Second tranche of ₹14 Lakh received.

August 2025

CSL CSR team site visit — progress reviewed on site.

Aug – Sep 2025

Shuttering and RCC roof slab cast and cured.

26 January 2026

Completed and inaugurated on the 77th Republic Day.

How It Was Managedप्रबंधन

We ran the construction ourselves

Not because it was easier, but because it gave us control over cost and quality.

The procurement decision

  • Invited quotations from construction agencies and labour contractors
  • Held several rounds of discussion with each, then visited their ongoing and completed sites in person
  • Compared labour-rate and labour-plus-material options on cost and quality
  • Engaged an experienced local labour contractor, and bought all materials directly from the local market
  • Refined the building map by re-measurement, with detailed structural, electrical and sanitary design before work began

What went wrong

The work took longer than we estimated. A state-wide strike by suppliers of building materials — particularly bajri and stone — stopped supply, and labour shortages followed. Progress slowed through the middle of the year.

We report this because a partner is entitled to know how an implementing agency behaves when a project slips. The building was completed to the specified quality and handed over in time for the Republic Day inauguration, and the grant was utilised in full.

The Moneyव्यय विवरण

Where the ₹40 Lakh went

The approved budget, as submitted and as spent.

Construction — 1,517 sq. ft. (design, civil engineering, labour contractor, materials)
34,89,100
Electrical wiring, fans and lights, water and sanitary fittings
2,50,000
Health centre furniture and fixtures
1,00,000
Computer and printer
1,00,000
Inauguration function
41,000
Chartered Accountant, accountant fees and miscellaneous
20,000
Total
₹40,00,100

The grant was released in tranches — ₹20 Lakh in January 2025 and ₹14 Lakh in August 2025 — both fully utilised, with the balance also spent to complete the project. The Statement of Expenditure and Utilisation Certificate, together with the stage and completion report signed by the registered engineer and architect, were submitted to Cochin Shipyard Limited.

Documented Throughoutप्रमाण

Photographed at every stage

The full construction sequence is in the FY 2025-26 Annual Report.

The completed Kendra at the Hathikhera campus
The completed Kendra at the Hathikhera campus
Unveiling the donor recognition plaque
Unveiling the donor recognition plaque
Cochin Shipyard Limited's recognition board at the entrance
Cochin Shipyard Limited's recognition board at the entrance
For Your Next Partnerसाझेदारी

What this demonstrates

Compliance in place

  • CSR-1 registered with the Ministry of Corporate Affairs (CSR00058152)
  • 80G and 12A approvals current; FCRA registered
  • Accounts audited by a firm of Chartered Accountants and filed annually
  • Registered under the Rajasthan Public Charitable Trust Act 1959

Reporting you can file

  • Statement of Expenditure and Utilisation Certificate
  • Stage and completion reports signed by a registered engineer and architect
  • Photographic documentation at every construction stage
  • Donor recognition displayed on site, using content the donor approves

Discuss a partnership

We are open to funding a defined piece of work with an agreed budget, timeline and reporting schedule — as above. Tell us what your CSR committee needs to see.